Wooten Company Presents Scaled-Down Phase One Plan for Water Street Corridor
PLYMOUTH — The Plymouth Town Council received a detailed presentation Monday evening on the long-awaited downtown streetscape project, which has been reduced in scope due to rising construction costs but remains a significant investment in the town’s economic future.
Lester Lowe of the Wooten Company presented the current vision for what is now designated as Phase One of the streetscape improvement project. The work will focus on a single block along Water Street from Adams Street to Washington Street, representing a scaling back from the original four-block plan conceived in 2018.
A copy of the proposal presented to council appears below this story.
“When we first started this, we were looking at four blocks of the downtown doing most sides of the road. Today’s dollars, we’re going to do one block,” Lowe explained to the council.
The project, funded through two grants totaling approximately $800,000, combines a North Carolina Main Street Rural Transformation Grant of $735,000 with an additional $300,000 emergency funding cycle grant. The emergency funding was made necessary after construction costs increased by as much as 300% in some areas following the COVID-19 pandemic, according to Mayor Brian Roth.
Project Features and Design Elements
The streetscape improvements will extend “from the back of the curb to the building face” and include several key components:
- New LED streetlights with decorative poles that can accommodate banners and Christmas lighting with built-in electrical receptacles
- Brick paver walkways with mixed color patterns and borders for visual contrast
- Tree plantings with flush-mounted uplighting systems
- Electrical pedestals for food trucks and vendor events, with options for both standard and higher-amperage connections
- New benches and trash receptacles with anti-vandalism features
- ADA-compliant crosswalk improvements
The design emphasizes durability and maintainability, with products selected to be serviceable by local staff rather than requiring specialized contractors. All materials must comply with federal “Build America Buy America” requirements, meaning products must be manufactured in the United States.
Long-Term Vision Remains Intact
Despite the reduced initial scope, town officials emphasized that this represents the first phase of a comprehensive downtown revitalization effort. Plymouth has maintained a relationship with the North Carolina Main Street program for 15 years, positioning the town for future funding cycles.
Once the first phase is complete, the town will go through the Main Street’s grant funding cycle.
The project team expects to have 90% construction-ready plans completed within 45 days, with construction potentially beginning in early 2025. The timeline is designed to complete the work before major town events such as the Bear Festival.

Town Addresses Stormwater Infrastructure Challenges
Earlier in the meeting, Tracy Jones of G3 Engineering and Survey presented the town’s comprehensive stormwater action plan. The two-phase project will assess Plymouth’s drainage infrastructure and provide solutions for chronic flooding issues.
The assessment phase includes data collection on major outfalls to the Roanoke River and Conobee Creek, with particular attention to problem areas identified by Public Works Director Mike Godwin on Fourth Street, General Pettigrew Drive, and Wilkes Avenue.
G3 will conduct hydrologic and hydraulic modeling to identify problem areas, engage the public through an online reporting tool, and ultimately deliver a prioritized project list, best management practices manual, and one shovel-ready design project. The work is grant-funded with a completion deadline of June 2026.
Jones emphasized the importance of community input, noting that residents can report drainage issues through a QR code-accessible online survey or by speaking directly with field crews during data collection.
Tax Collection and Property Management Issues
The council also received an extensive briefing from Mark Bardwell of Zacchaeus Legal Services regarding delinquent property tax collection and foreclosure procedures. The firm represents 49 counties and towns across North Carolina in property tax enforcement.
Bardwell explained that Plymouth faces particular challenges with “problem parcels” – properties with complex ownership situations, often involving multiple heirs, that make traditional foreclosure procedures difficult or cost-prohibitive.
Town Manager Joanna Radford noted that some properties have as many as 47 heirs, requiring extensive legal notification processes. The town is considering adopting “in rem” foreclosure procedures for the most challenging cases, which could cost approximately $100 per party involved but would help clear long-delinquent properties from the tax rolls.
The council approved the release of five uncollectable tax accounts totaling less than $300, all more than 10 years old and legally uncollectable due to statutory limitations.
Other Council Business
- New RV Park Approved: The council unanimously approved a rezoning request for 870 US 64 West, allowing the development of “Black Bear RV Park” – a recreational vehicle park and campground facility.
- Police Department Staffing Update: Police Chief Louis Banks reported progress in addressing the department’s staffing shortage, with three experienced officers in the hiring process. Two former Plymouth officers are expected to return to duty within two weeks, with a third officer set to start within a month. This will bring the department above half-staffing levels for the first time in an extended period.
- Community Center Progress: Cedric Wilkins thanked the council for approving use of the Allied building as a community center, emphasizing that the facility will serve all citizens regardless of background. The center is currently seeking community input on preferred activities and programming.
- Public Works Updates: Public Works Director Michael Wright reported that all seven priority streets have been repaved, playground equipment has been ordered for Plymouth Community Park, and the major sewer infrastructure project on Roanoke Avenue is proceeding toward a 2026 construction timeline.
The next council meeting is scheduled for October.